Short answer: To compare two solar quotations fairly, first make sure both quote the same DC capacity (kWp) for the same roof, then compare line by line: panel make, model and wattage; inverter make and AC rating; mounting structure height and material; cables, earthing and protection devices; net-metering and subsidy paperwork; GST; and warranty and service terms. A lower total is only cheaper if the scope is the same.

Why two solar quotes for the same house can look so different

When a Hyderabad homeowner asks two installers for a 5 kW rooftop solar system, it is common to receive prices that differ significantly. Usually, neither installer is hiding anything. The difference comes from scope: one quote may include an elevated structure, lightning protection and the full TGSPDCL net-metering process, while the other prices only panels, an inverter and a basic frame.

A headline "per kW" price tells you very little until you know what is included. The checklist below helps you put two proposals side by side.

Step 1: Confirm both quotes are for the same system size

  • DC capacity (kWp): number of panels × panel wattage. Ten 550 W panels = 5.5 kWp.

  • Inverter AC rating (kW): a 5 kW inverter with 5.5 kWp of panels is a normal design choice, but the quote should state both numbers.

  • Expected generation: ask each installer for their estimated annual units and the assumptions behind it. See how solar generation and savings are estimated.

If one quote is for 5 kWp and the other for 5.5 kWp, convert both to a price per kWp before comparing.

Step 2: Compare the solar panels

  • Make and exact model: A model number you can look up, not just "Tier-1 panels"

  • Wattage and technology: e.g. 550 W mono PERC vs 580 W TOPCon

  • DCR or non-DCR: Subsidised home systems under PM Surya Ghar need domestically manufactured (DCR) panels

  • Product and performance warranty: Both should be written in the quote, with who handles a claim

  • Datasheet: Ask for it; dimensions affect how many panels fit your roof

Step 3: Compare the inverter

  • Make, model and AC capacity

  • Single-phase or three-phase, matched to your electricity connection

  • On-grid or hybrid (battery-ready). A hybrid inverter costs more; see on-grid vs hybrid solar

  • Monitoring: Wi-Fi/app included or extra

  • Warranty period and whether an extension is offered

Step 4: Compare the mounting structure

The structure is where quotes differ most and where corners are easiest to cut.

  • Height: a low structure is cheaper; an elevated structure keeps the terrace usable and costs more.

  • Material and finish: hot-dip galvanised steel or aluminium, with the coating thickness stated.

  • Fixing method: chemical anchors or ballast, and who is responsible if the terrace waterproofing is affected.

  • Wind loading: ask whether the design has been checked for your building height.

Step 5: Compare cables, earthing and protection

A safe, long-lasting system needs more than panels and an inverter. Check whether each quote lists:

  • DC and AC cables (solar-rated, with sizes)

  • DC distribution box (DCDB) and AC distribution box (ACDB) with surge protection

  • Earthing pits for the panel structure and inverter

  • Lightning arrester, where the site needs one

  • Conduits, cable trays and labelling

If one quote lists these items and the other does not, ask the second installer in writing whether they are included.

Step 6: Compare paperwork, approvals and subsidy support

  • TGSPDCL net-metering application and liaison

  • PM Surya Ghar portal registration and subsidy documentation (homes only)

  • Net meter cost: who pays and who arranges it

  • Inspection and commissioning documents

The subsidy is credited to the homeowner's bank account after commissioning is approved, so a quote should show the full price before subsidy and the expected subsidy separately. Read our PM Surya Ghar guide and net metering in Telangana.

Step 7: Compare GST, payment terms and exclusions

  • Is GST included in the total, and at what rate is it shown?

  • Payment schedule: advance, on material delivery, on commissioning

  • Exclusions: civil work, load enhancement fees, extra cable runs, waterproofing, transport

  • Validity date of the quote (equipment prices change)

Step 8: Compare warranty, service and handover

  • Workmanship warranty from the installer, in years

  • Annual maintenance or cleaning visits included, if any

  • Response time for breakdowns

  • Handover documents: serial numbers, warranty cards, single-line diagram and monitoring login. See plan solar maintenance before the installation

A side-by-side comparison checklist

Write down each of these for Quote A and Quote B:

  • DC capacity (kWp)

  • Panel make / model / wattage / DCR

  • Inverter make / model / kW / phase

  • Structure height and material

  • ACDB, DCDB, surge protection, earthing, LA

  • Net metering and subsidy paperwork

  • GST included?

  • Total price before subsidy

  • Price per kWp

  • Workmanship warranty

  • Exclusions

Red flags in a solar quotation

  • No panel or inverter model number

  • Only a price per kW with no item list

  • A price shown "after subsidy" without the full pre-subsidy amount

  • Generation promises with no assumptions behind them

  • No mention of earthing or surge protection

  • Pressure to pay a large advance before a site survey

Frequently asked questions

What should a solar installation quotation include?

The DC capacity, panel and inverter make and model, mounting structure details, cables and protection devices, net-metering and subsidy support, GST, payment terms, exclusions and warranties.

Is the cheapest solar quote the best value?

Only if its scope matches the other quote. Price differences usually come from the structure, protection equipment, panel technology and the paperwork included.

Should I compare solar quotes by price per kW?

Yes, but only after confirming both quotes have the same DC capacity and scope. Use price per kWp (DC) for a fair comparison.

Should the quote show the subsidy separately?

Yes. Under PM Surya Ghar the subsidy is paid to the homeowner after commissioning, so the quote should show the full price you pay first and the expected subsidy as a separate line.

Do I need a site survey before a final quotation?

Yes. Roof space, shading, structure height and cable routes can only be confirmed on site, so a final quote should follow a survey.

Related guides

Get a quotation you can compare line by line

Arkasri Energy provides itemised rooftop solar quotations for homes, villas and businesses across Hyderabad and Telangana, after a site survey. See rooftop solar for homes, check the solar panel cost guide, or book a site assessment.

Written by the Arkasri Energy team, Tellapur, Hyderabad. Reviewed November 2026. Confirm subsidy and net-metering rules with the official portal and TGSPDCL before you apply.