Short answer: An end-to-end solar company in Hyderabad takes responsibility for every stage of a rooftop project: reviewing your bills and sanctioned load, surveying the roof, designing the system, applying to TGSPDCL and (for homes) the PM Surya Ghar portal, supplying and installing equipment, arranging inspection and the net meter, submitting commissioning documents, and handing over with monitoring and warranties. You still provide documents, roof access and decisions. A typical home project takes around two to three months, mostly waiting for approvals.

Who is involved

  • You (the owner): bills, documents, roof access, decisions and payment

  • The solar EPC company: design, procurement, installation, paperwork and handover

  • TGSPDCL: feasibility, inspection, net meter and approval

  • PM Surya Ghar portal (homes): registration, vendor selection and subsidy

  • Electrical inspectorate: certification for larger systems (above 56 kWp)

Stage by stage

  1. Bill and load review — Installer, with your 12 months of bills. Confirms sanctioned load and phase. See sanctioned load and solar capacity.

  2. Site survey — Installer. Roof, shading, structure height, cable routes and inverter location. See what a site survey checks.

  3. Design and quotation — Installer. Layout, equipment, itemised price. See comparing quotations.

  4. Contract — You and installer. Scope, milestones, timelines, warranties. See what your solar contract should say.

  5. Load enhancement, if needed — You, with installer support, applied to TGSPDCL.

  6. Application — Installer: PM Surya Ghar portal for homes, TGSPDCL net-metering application for others. See net metering in Telangana.

  7. Feasibility approval — TGSPDCL. Checks transformer capacity and documents.

  8. Procurement — Installer. ALMM/DCR-compliant panels, inverter, structure and protection. See DCR vs non-DCR.

  9. Installation — Installer. Usually a few days for a home. See installation quality checklist.

  10. Inspection and net meter — TGSPDCL, with installer documents.

  11. Commissioning approval and subsidy — TGSPDCL and the portal; subsidy credited to your bank. See avoiding subsidy delays.

  12. Handover — Installer. Monitoring login, serial numbers, warranties, single-line diagram. See maintenance and handover.

  13. After-sales support — Installer or AMC provider. See solar AMC in Hyderabad.

How long does the full process take?

  • Survey, design and contract: about one to two weeks, depending on your decisions

  • Approvals: the DISCOM has 15 working days to issue feasibility once an application is complete under the 2025 regulation

  • Installation: a few days for a typical home once materials arrive

  • Inspection, net meter and subsidy: often the longest wait

Installers in Hyderabad commonly report around two to three months in total for a home. Load enhancements, document mismatches and transformer capacity can add time.

What "end-to-end" should not mean

  • It does not mean you sign without seeing an itemised scope

  • It does not guarantee approval timelines, which depend on TGSPDCL

  • It does not replace your own check of equipment and warranties

Frequently asked questions

What does an end-to-end solar company do?

It handles survey, design, approvals, supply, installation, inspection, commissioning paperwork and handover, so you deal with one accountable company.

Does a turnkey solar quote in Hyderabad include net metering?

It should state this clearly. Check whether the application, liaison and net meter cost are included.

Who handles subsidy documents in an end-to-end project?

Usually the registered vendor, using documents you provide. The subsidy is paid to your bank account.

How long does rooftop solar take in Hyderabad?

Often around two to three months for a home, mostly approvals. Installation itself takes a few days.

Who is responsible for utility approvals?

TGSPDCL grants them; the installer usually prepares and submits the application and documents.

Related guides

One company, every stage

Arkasri Energy is an end-to-end solar EPC company in Hyderabad covering homes, businesses and institutions. Read the Hyderabad rooftop solar buyer's guide, learn what solar EPC involves, or book a site assessment.

Written by the Arkasri Energy team, Tellapur, Hyderabad. Reviewed November 2026. Approval timelines depend on TGSPDCL and the portal.